Critical Path Method
Critical Path Method -Part I
Calculate the expected time (hours, days, weeks, or whatever) for the following tasks. Report the time to the next highest whole number.
Task | Optimistic (shortest) Time | Most Likely Time | Pessimistic (longest) Time | Expected Time (answer) |
A | 3 | 5 | 7 | |
B | 10 | 15 | 20 | |
C | 4 | 5 | 6 | |
D | 27 | 45 | 90 | |
E | 8 | 9 | 12 | |
F | 81 | 93 | 98 |
Part II
Each of these CPM diagrams corresponds to one of the task lists given below. Match them. Ex. A:#, B:#, etc. Symbols:START END |
A. | B. |
C. | D. | E. |
Part III
Part IV
Estimated and crash costs for each task are shown in the table below.
Answer the questions below the table.
Version 1 | Original Estimates | Crash Estimates | Crash Differentials | ||||
Task
(T) |
CP
* |
Est. Time,
weeks (ET) |
Est. cost,
$1000, (EC) |
Crash
Time, weeks (CT) |
Crash
Cost, $1000 (CC) |
Time
saved
(ET-CT) |
Extra
cost
(CC-EC) |
A | * | 5 | 10 | 4 | 12 | ||
B | * | 7 | 15 | 5 | 17 | ||
C | 5 | 8 | 3 | 12 | |||
D | * | 6 | 6 | 5 | 8 | ||
E | * | 9 | 12 | 8 | 15 | ||
F | 4 | 16 | 2 | 20 | |||
G | * | 5 | 20 | 2 | 21 | ||
(End) | – |
CP=Critical Path. If task is on CP, then *; otherwise blank.
- Fill in the blank cells under Crash Differentials.
- Instead of the scheduled 7 weeks, Task B took 9 weeks. Which task or tasks should be crashed to make up the lost time, at minimum cost? Explain.
Assignment Expectations
- There are no page limits. Write what you need to write, neither more nor less. Make each sentence count! (Having said that; it’s unlikely that one page would be enough, and very likely that eight pages would be too much.)
- Ensure that your answer reflects your detailed understanding of the theory and techniques taught in this module.
- References and citations are required. This requirement can be satisfied by citing the module Home page.
Answer Preview-Critical Path Method
$9.00